CMM Sitework, Inc was hired to take over from an existing Sitework contractor in November 2015. We started by correcting and establishing sub grades for the entire property, installing a construction entrance and tracking pad, removing and disposing of existing concrete piling caps and excavating for the completion of grade beams. CMM Sitework installed (64) drywells and approximately 2800 Linear Feet of PVC interconnecting pipe, we also installed two sanitary systems and coordinated all inspections. We excavated and backfilled for retaining walls and precast geothermal control valve vault. The job has currently been put on hold; we hope to be back on site in the near future.