Projects

Our Projects

CMM Sitework, Inc. is a well established excavation and drainage firm serving Long Island. Trusted and recommended since 2005,

Pheasant Lane Residence

May 2015

Location: Southampton, NY • Project Duration: 13 Months

CMM Sitework started working on this project in May of 2015. There was an existing house on the site that was demolished and removed, we then stripped and stockpiled approximately 3000 cubic yards of topsoil. We then excavated for a 5000 Sq. Ft. 12’ deep foundation and then provided the equipment and labor necessary to backfill and compact.
We excavated for a sunken tennis court and a pool house with a full foundation basement underneath it. CMM Sitework installed conventional septic systems for both the main house and the pool house. CMM Sitework also installed all of the necessary drywells for the main house, pool house and the sunken tennis court, including PVC piping. We imported and graded approximately 2,500 cubic yards of fill and used all excavated materials on the site to establish final sub grades.

Del Vino Vineyards

June 2017

Location: Northport, NY • Project Duration: 5 Months

CMM Sitework, Inc. started working on this Vineyard in June 2017. We started with constructing an access road and installing wire backed silt fencing. We trenched and backfilled for temporary pump house electric system in order to keep the water supply working in the vineyard during construction. We removed and disposed of the foundation beneath the existing house that was raised by a house-lifting contractor.
CMM Sitework, Inc. started working on this Vineyard in June 2017. We started with constructing an access road and installing wire backed silt fencing. We trenched and backfilled for temporary pump house electric system in order to keep the water supply working in the vineyard during construction. We removed and disposed of the foundation beneath the existing house that was raised by a house-lifting contractor. We excavated for the new foundation under the house and all the new additions. We furnished and installed several storm water drywells from parking lot drainage. We also installed two sanitary systems consisting of grease traps, septic tanks, leaching pools and PVC piping, we then abandoned the existing septic systems. Excavated and backfilled for water service and fire sprinkler supply line. CMM Sitework, Inc. then supplied equipment and labor to install an electric manhole and transformer pad. CMM Sitework, Inc. completed their scope of work on time and on budget in December 2017.

Bull Path Residence

Feb 2018

Location: Southampton, NY • Project Duration: 15 Days

CMM Started working on Bull Path in February 2018. We are currently working on two properties along side each other. CMM started both properties by removing trees, stumps and root matt from both the building lots and the common driveway within Town restricted clearing limits. Both lots and common driveway had very challenging topographies.
Because access to both lots was going to be difficult we chose to install all underground utilities coming down the common driveway, prior to creating a stable accessible roadway, this was we wouldn’t have to disturb the road once it was established. The project was done in the middle of winter, therefore we had to pay close attention to managing mud on the job site to prevent trades from getting stuck and from tracking onto the street.

24 Hour Fitness

134 Murray Lane, Southampton

Amazon - 91 Precision Dr.

Huntington Hotel

Jericho Schools

Robert's Asphalt

Surf Lodge, Montauk

Call us

VISIT US

Copyright © CMM Sitework All Rights Reserve